Lean Manufacturing
What lean manufacturing is, which wastes it targets and why smaller batches pay off only after changeovers get shorter.
04. november 2026
2 min

Lean manufacturing is a production philosophy that organizes work around the flow of value to the customer and removes activities that consume time or resources without adding value. It originates in the Toyota Production System and treats overproduction, waiting and excess inventory as waste to be eliminated.
Lean names seven classic wastes: overproduction, waiting, transport, overprocessing, inventory, motion and defects. Its tools follow from them: value stream mapping to see where lead time is lost, pull control with kanban instead of producing to a forecast, smaller batches, quick changeovers (SMED), standardized work and continuous improvement (kaizen).
Lean manufacturing in practice
Smaller batches are where lean meets arithmetic. A line runs its products in batches of 2,000 units and changes over 8 times a week at 60 minutes each, so 8 hours a week go to changeovers. Halving the batch to 1,000 units halves the average cycle stock of each product and shortens the wait for the next run, but it doubles changeovers to 16 a week, or 16 hours. If the line is the bottleneck, those extra 8 hours come straight out of plant output. Smaller batches pay off once changeover time has fallen, here to 30 minutes, which keeps the weekly total at 8 hours. That is why SMED comes before batch reduction, not after it.
The second limit is the word inventory. Lean targets stock made ahead of demand and work‑in‑process waiting between operations. Safety stock that covers variability in demand or supplier lead times is a different thing: cutting it without reducing that variability moves the problem into stockouts, expediting or overtime. Lean also assumes fairly level demand (heijunka). Where demand swings with promotions or seasons, the buffer in front of the constraint protects output and needs to be sized, not removed.
Logio maps material flow and tests changes such as batch size, buffer placement or a new layout with dynamic simulation before they reach the shop floor, as part of intralogistics and material flow and production capacity planning projects.
Related terms
More supply chain insights

Supply chain glossary
Order Picking
What order picking is, why the number of lines per order decides between single‑order and batch picking, and why output is measured in lines per hour.
17. november 2026
3 min

Supply chain glossary
Goods‑to‑Person (G2P)
What goods‑to‑person picking is, why order batching at the station decides how much automation a warehouse needs and which items stay outside the system.
16. november 2026
3 min

Supply chain glossary
AS/RS
What an automated storage and retrieval system is, why its number of aisles follows peak‑hour throughput and how one crane per aisle shapes the failure mode.
15. november 2026
3 min