3PL & contract logistics

Balanced workload across the DC

Logio analyzed last season’s pick heatmaps and flow to redesign slotting and introduce active wave management ahead of Black Friday.

Outcome

The plan prevents overload at any workstation, evens out throughput across zones, and uses capacity and labor efficiently.

About DHL

DHL is the world’s leading logistics company, providing international express delivery, freight transportation, e‑commerce fulfillment and contract logistics services as part of DHL Group. The Group operates in more than 220 countries and territories and employs around 600,000 people worldwide. In 2023, DHL Group reported revenue of 81.8 billion euros.

 

Approximately 600,000 employees worldwide

Operations in over 220 countries and territories

81.8 billion EUR in group revenue in 2023

Initial challenge

A Czech DHL Supply Chain distribution center was overloaded in the previous Black Friday season. The site faced delivery delays, higher picking errors, and customer dissatisfaction.

Project goal

Prepare the site for the next peak. Balance workload across workstations, increase flow through the warehouse, and use capacity and resources effectively.

Solution

Smarter flow for stable peaks

Logio combined historical pick heatmaps and operational data with SKU categorization and expected peak flow to redesign slotting and implement active wave management.

01

Data intake

and analysis of last season’s picking heatmaps to locate bottlenecks and unused capacity.

02

SKU categorization

and calculation of expected peak‑season flow by zone.

03

Re‑slotting key

for flow racks aligned to inventory turns and access frequency.

04

Active pick‑wave

control to keep every workstation within safe capacity bands.

Solutions implemented

Production & Automation Design

Process Mapping & Analysis

Capacity Planning

Impact

Peak‑season ready operations without adding headcount.

Even workload across zones

Active wave control levels work and reduces bottlenecks.

Shorter travel paths for pickers

Re‑slotting reduces zig‑zag movement and empty walking.

Make your warehouse peak‑ready

If your DC strains during promotions or Black Friday, we can rebalance flow, redesign slotting, and stabilize waves. Let’s talk about a data‑driven plan for your next peak.

420

By submitting, you agree to our Privacy Policy and allow Logio to contact you.

We tackled many supply chain challenges

Automation feasibility study for DHL Supply Chain

Logio delivered an independent feasibility study for DHL Supply Chain, evaluating warehouse automation options and producing a conceptual solution design with realistic development scenarios and investment guidance.

Independent assessment of automation options delivered

Conceptual solution design and investment framework completed

Defined next‑step roadmap including technical due diligence and tendering guidance

Show case study

Production ramp up support for Grupo Antolin Turnov

Grupo Antolin Turnov secured the on‑time launch of a new automotive interior production line by combining crisis management, material flow design and dynamic simulation with Logio’s support. The project delivered a validated logistics concept and reduced risk at start‑up.

New interior production started on the original target date.

New logistics concept for the line prepared, implemented and executed.

Key risks and bottlenecks verified and mitigated in simulation before go‑live.

Show case study